Aspiration Kanban

The Aspiration Kanban is a 4-column view of the Aspiration Backlog, the backlog that contains all the ideas, initiatives, ambitions, projects, etc. a company thinks are necessary to fulfill its strategy/vision.

Such ideas, initiatives, ambitions, projects etc. share a generic name: aspiration

The kanban provides a handy view on everything the company is working on according to their phase:

  • bubble: the aspiration hasn't been examined at all. It is mentioned merely to avoid forgetting about it but no one knows what must be done precisely
  • to-start: the aspiration has been examined and must be started as soon as the Value Stream has capacity to start it
  • started: the aspiration has started
  • closed: the aspiration has been brought LIVE and is closed (a Closure Report is available)
Bubble To Start Started Closed
IT Transformation and Modernization (P1) – (01/04/2019-01/12/2019 – FGTB-00002) . (Patrick Boens) R
+1
  MyABVV (P1) – (01/01/2019-30/06/2019 – FGTB-00004) . (Rudi Vandeweyer) R


EC6 (P1) – (29/04/2019-30/06/2019 – FGTB-00005) . (Patrick Boens) R


FGTB Web Site (P2) – (01/04/2019-31/12/2019 – FGTB-00001) . (Patrick Boens) R


FGTB PMO (P3) – (01/04/2019-31/12/2019 – FGTB-00000) . (Patrick Boens) R


+4
 

It took 0.8002 sec to render the Kanban

Portfolio Roadmap (01-12-2018 ― 31-12-2020)

MyABVV - P1 - FGTB-0000401-01-2019 – 30-06-2019FGTB PMO - P3 - FGTB-0000001-04-2019 – 31-12-2019FGTB Web Site - P2 - FGTB-0000101-04-2019 – 31-12-2019IT Transformation and Modernization - P1 - FGTB-0000201-04-2019 – 01-12-2019EC6 - P1 - FGTB-0000529-04-2019 – 30-06-2019Dec
2018
 
Jan
2019
 
Feb
2019
 
Mar
2019
 
Apr
2019
 
May
2019
 
Jun
2019
 
Jul
2019
 
Aug
2019
 
Sep
2019
 
Oct
2019
 
Nov
2019
 
Dec
2019
 
Jan
2020
 
Feb
2020
 
Mar
2020
 
Apr
2020
 
May
2020
 
Jun
2020
 
Jul
2020
 
Aug
2020
 
Sep
2020
 
Oct
2020
 
Nov
2020
 
Dec
2020
 
Jan
2021
 
 
 

Legend

 Bubble

 To start

 Started

 Closed


 Late

 Not started yet and should have been started


 Frozen

 Postponed

 Abandoned


 RAG: Red

 RAG: Amber

 RAG: Green

Aspirations in Difficulties

  • MyABVV (FGTB-00004) (led by Rudi Vandeweyer): The last finished sprint of the project (14-06-2019) has a R RAG (status: at-risk) (started)
  • FGTB PMO (FGTB-00000) (led by Patrick Boens): The last finished sprint of the project (07-06-2019) has a R RAG (status: at-risk) (started)
  • FGTB Web Site (FGTB-00001) (led by Patrick Boens): The last finished sprint of the project (10-05-2019) has a R RAG (status: at-risk) (started)
  • IT Transformation and Modernization (FGTB-00002) (led by Patrick Boens): The project should have been started since 01-04-2019 (bubble)


Top

Notre site utilise des cookies pour sauver vos préférences et RIEN d'autre. Nous vous demandons de bien vouloir accepter les cookies qui sont positionnés sur notre site et nous vous promettons en retour de ne RIEN laisser transparaître de votre parcours de visite, dont d'ailleurs vous nous faites l'honneur. Au cas où néanmoins vous n'accepteriez pas d'utiliser les cookies, vous aurez probablement une navigation LÉGÈREMENT dégradée sur notre site. Bonne visite!X